Project
Completed

GAIL GANDHAR GAS PROCESSING PROJECT

GAIL GANDHAR GAS PROCESSING PROJECT

Name of work
Electro Mechanical Erection works for Gail Gandhar Gas Processing Unit.
Site
Gandhar. U.P.
Client
M/s Gas Authority of India Limited, New Delhi.
Customer
M/s Gas Authority of India Limited, New Delhi.
Project Duration
12 Months.
Our Scope of Work
Fabrication & Erection of Piping & related Civil works. Erection of Equipments, Structural, RCC, Cold Insulation and Painting. Supply & Installation of Transformers, Panels & Switch board. Installation of Cable, Cable Tray, Termination & Lighting.
Contract Value
8.15 Crores.
 
 
Date of Completion
2001.