Project
Completed

Balance of Plant (BoP) packages for 2 x 300 MW JSW Energy Vijayanagar Thermal Power Plant Project

Balance of Plant (BoP) packages for 2 x 300 MW JSW Energy Vijayanagar Thermal Power Plant Project

Name of work
LSTK of Balance of Plant (BoP) packages and Erection, Testing & Commissioning of BTG & its Auxiliaries for 2 x 300 MW Thermal Power Plant Project
Site
Toronagallu, Bellary District, Karnataka, India
Client
M/s. JSW Energy (Vijayanagar) Ltd
Customer
M/s. JSW Energy (Vijayanagar) Ltd
Project Duration
Our Scope of Work
Erection of BTG & its Auxiliaries, ESP Design, Engineering, Supply and Erection of Balance of Plant (BoP) Packages Coal Handling Plant Ash Handling Plant Cooling Water System HVAC System Piping Air Compressor System Fire Fighting System Fuel Oil Unloading system Miscellaneous packages, Civil works BoP Electrical BoP (E-BoP) and associated Control & Instrumentation works

 

Date of Completion
2009