1 X 660 MW Panki Thermal Power Project, Panki - BHEL
Name of work
Power Cycle Piping
Site
1 X 660 MW Panki Thermal Power Project, Panki
Client
Bharat Heavy Electrical Limited
Customer
Uttar Pradesh Rajya Vidyut Utpadan Nigam
Project Duration
22 Months
Our Scope of Work
Erection, Testing, Commissioning, Trial Operation and Handing Over of Power Cycle Piping, all associated Piping & Equipment, Insulation and Final Painting Including Supply Of Paints For 1 X 660 MW Panki Thermal Power Project, Panki, Kanpur, UP