Power

THERMAL POWER PROJECTS

Name of work
Mechanical Erection, Testing and Commissioning of Boiler & its Auxiliaries, ESP for Unit- I & LP Piping for Unit 1 & 2 of 2 x 600 MW Stage-II, TNEB North Chennai Thermal Power Project

Site
Athipattu,Tamil Nadu, India

Client
M/s. BHEL-PSSR, Chennai

Customer
M/s. TANGEDCO Ltd. (TNEB)

Project Duration
36 Months

Our Scope of Work
Boiler & its auxiliaries, ESP,Rotating Equipments, cooling water piping, Balance LP Piping

Date of Completion
2013
Name of work
Mechanical Erection,Testing and Commissioning of Boiler & its auxiliaries for Unit- III, Stage-II of 1 x 500 MW NTECL Thermal Power Plant Project.

Site
Kuruvimedu, Ponnery Taluk, Thiruvallur Dist., Tamil Nadu, India

Client
M/s. BHEL-PSSR, Chennai

Customer
M/s. NTPC Tamilnadu Energy Corporation Ltd (a NTPC-Tangedco JV)

Project Duration
31 Months

Our Scope of Work
Structures, Pressure Parts, Non-Pressure Parts, Air Pre Heaters, Ducts. Rotating equipments, etc.

Date of Completion
2015

1.png
Name of work
Mechanical Erection,Testing and Commissioning of Boiler & its auxiliaries for Unit- I, Stage-I of 2 x 500 MW NTECL Thermal Power Plant Project.

Site
Kuruvimedu, Ponnery Taluk, Thiruvallur Dist., Tamil Nadu, India

Client
M/s. BHEL-PSSR, Chennai

Customer
M/s. NTPC Tamilnadu Energy Corporation Ltd (a NTPC-Tangedco JV)

Project Duration
30 Months

Our Scope of Work
Structures, Pressure Parts, Non-Pressure Parts, Air Pre Heaters, Ducts. Rotating equipments,etc. 55TPH Auxiliary boiler


Date of Completion
2012
Name of work
Electro Mechanical Erection works for 2X500 MW Thermal Power Plant Project.

Site
Anpara, UP, India.

Client
M/s.Mitsui

Customer
M/s. Uttar Pradesh State Electricity Board, Anpara UP State, India.

Consultant
M/s. Central Electricity Authority of India, Delhi.

Project Duration
55 Months.

Our Scope of Work
  • Erection of Boiler & Auxiliaries, Presser parts, Structural, Piping & Equipments.
  • Erection of BoP System.
    1. Coal Handling Plant
    2. Switchyard-400 KV/132KV/33KV

Date of Completion
November 1995
Name of work
Mechanical Erection, Testing and Commissioning of Boiler & its Auxiliaries of Unit#3, Phase-II, 2 X 500MW for Simhadri Super Thermal Power project.

Site
Vishakapatnam, AP, India

Client
M/s. BHEL-PSSR, Chennai

Customer
M/s. National Thermal Power Corporation Ltd.,

Project Duration
24 Months

Our Scope of Work
Pressure Parts, Non-Pressure Parts, Air Pre Heaters, Duct etc.

Date of Completion
May 2010
Name of work
Mechanical Erection Testing and Commissioning of Boiler & itsauxiliaries for 2 x 300MW Thermal Power Plant Project

Site
Vijayanagar, Toronagallu, Bellary District, Karnataka, India

Client
M/s. JSW Steel Ltd

Customer
M/s. JSW Steel Ltd

Consultant
M/s. TCE, Bangalore

Project Duration
18 Months

Our Scope of Work
Boiler, Air Pre Heaters, ESP, Fuel Oil System, Critical Piping & Duct.

Date of Completion
2012
Name of work
Mechanical Erection Testing and Commissioning of BTG & itsauxiliaries for 210 MW Thermal Power

Site
Tuticorin, TN, India.

Client
M/s. BHEL, Chennai.

Customer
M/s. TNEB, TN.

Consultant
M/s. BHEL, Chennai.

Project Duration
14 months.

Our Scope of Work
Erection of Turbine Generator, Condenser, Pressure parts, Non-Pressure Parts, Structure, Ducting, Piping and Equipments. 

Date of Completion
1992
Name of work
Mechanical Erection Testing and Commissioning of Boiler & its auxiliaries for 210 MW Raichur Thermal Power Project.

Site
Raichur, Karnataka, India

Client
M/s. BHEL, Chennai.

Customer
M/s. Karnataka Electricity Board, Bangalore.

Consultant
M/s. BHEL, Chennai.

Project Duration
18 Months.

Our Scope of Work
Erection of Boiler & Auxiliaries, Structures, and Equipments works.

Date of Completion
October 1994
Name of work
Mechancial Erection, & assistance in commissioning of 1 x 563TPH PC fired Boiler at M/s. OPG Power Generation Pvt. Ltd

Site
Gummidipoondi, Chennai, TN, India

Client
M/s. ISGEC Heavy Engineering Ltd., Noida.

Customer
M/s. OPG Power Generation Pvt.Ltd., Chennai.

Project Duration
15 Months

Our Scope of Work
Boiler & its auxiliaries, ESP

Date of Completion
2015
Name of work
Mechanical Erection Testing and Commissioning of BTG & its Auxiliaries for 6 x 135MW Captive Thermal Power Plant Project

Site
Angul, Odisha, India

Client
M/s. Jindal Steel

Customer
M/s. Jindal Steel

Project Duration
26 Months

Our Scope of Work
Boiler & its auxiliaries, ESP
Turbine Generator & its auxiliaries


Date of Completion
2013
Name of work
Mechanical Erection works for 9X135 MW CPP Power Project.

Site
Jharsuguda, Orissa.

Client
M/s. SEPCO-III, China.

Customer
M/s. Vedanta, Mumbai.

Consultant
M/s. TCE, Bangalore.

Project Duration
26 Months

Our Scope of Work
  • Erection of 5 nos. of Boiler, Boiler Steel Structure, ESP, Piping, Auxiliary Equipments, Hoist & Painting works.
  • Erection of BoP System.
    1. Coal Handling Plant
    2. Coal Handling Equipments.
    3. Coal Processing Unit
    4. Conveying System

Date of Completion
October 2008
Name of work
Mechanical Erection Testing and Commissioning of BTG & its Auxiliaries for 2 x 135MW Captive Thermal Power Plant Project

Site
Raigarh, Chhattisgarh, India

Client
M/s. Jindal Steel

Customer
M/s. Jindal Steel

Project Duration
18 Months

Our Scope of Work
Boiler & its auxiliaries, ESP
Turbine Generator & its auxiliaries

Date of Completion
2010
Name of work
Mechanical Erection, Testing and Commissioning of Boiler & its Auxiliaries of Unit#3, Phase-II, 2 X 500MW for Simhadri Super Thermal Power project.

Site
Vishakapatnam, AP, India

Client
M/s. BHEL-PSSR, Chennai

Customer
M/s. National Thermal Power Corporation Ltd.,

Project Duration
24 Months

Our Scope of Work
Pressure Parts, Non-Pressure Parts, Air Pre Heaters, Duct etc.

Date of Completion
May 2010
Name of work
Mechanical Erection Testing and Commissioning of Boiler & itsauxiliaries for 1 x 500 MW Thermal Power Project.

Site
Simhadri, AP, India.

Client
M/s. BHEL, Chennai

Customer
M/s. NTPC

Consultant
M/s. NTPC.

Project Duration
27 Months

Our Scope of Work
Erection of Presser parts, Drum, Structural Gallery, Ducts, Main Steam Piping, Staircase & Miscellaneous equipments.
cosplay genshin impact

Date of Completion
December 2002
Name of work
Mechanical Erection works of CFBC Boiler & its Auxiliaries for 2 x 250 MW Lignite based Power Plant Project.

Site
Neyveli, Cuddalore District, TN, India

Client
M/s. BHEL - PSSR, Chennai

Customer
M/s. Neyveli Lignite Corporation Ltd, Chennai

Project Duration
22 Months

Our Scope of Work
Structure, Pressure Parts, Non- Pressure Parts, ESP, Bunkers, Fans, Fuel Oil Systems and Equipments

Date of Completion
July 2015
Name of work
Mechanical Erection works for 2X135 MW CPP Power Project.

Site
Korba, India.

Client
M/s. SEPCO, China

Customer
M/s. BALCO, Korba

Project Duration
16 Months.

Our Scope of Work
  • Erection of Presser parts, ESP, Ducts & Tanks.
  • Erection of BoP system.
    1. Coal Handling Plant
    2. Ash Handling Plant
cheap jerseys

Date of Completion
December 2005
Name of work
Mechanical Erection works for 2X125 MW lignite based Power Plant Project

Site
Akrimota, Gujarat.

Client
M/s. ALSTOM Power Boilers Services Ltd., Calcutta.

Customer
M/s.Gujarat Minerals Development Corporation

Consultant
M/s. Alston Power, Calcutta.

Project Duration
36 Months.

Our Scope of Work
  • Erection of Presser parts, ESP, Structural, Ducts, Cyclone & Piping works.
  • Erection of BoP System.
  1. Ash Handling Plant

Date of Completion
March 2006
Name of work
Mechanical Erection of Boiler Unit-I and BoP Equipments for Lara Super Thermal Power Plant Project (800MW x 2 Unit).

Site
Lara Village, Raigarh district, Chhattisgarh, India.

Client
M/s. Doosan Power Systems India Pvt Ltd

Customer
M/s. NTPC Ltd.

Project Duration
36 Months

Our Scope of Work
 - Boiler & its Auxiliaries
 - BoP Equipment erection

Date of Completion
DECEMBER 2017
Name of work
Mechanical Erection of Boiler Unit II for Kudgi Super Thermal Power Plant Project stage - I (800MW x 3 Unit).

Site
Kudgi Village, Bijapur district, Karnataka, India

Client
M/s. NTPC Ltd.

Customer
M/s. Doosan Power Systems India Pvt Ltd

Project Duration
36 Months

Our Scope of Work
 - Boiler & its Auxiliaries
replica chopard

Date of Completion
2018
Name of work
Erection of Main Engines & Accessories, Fabrication and Erection of Pipelines, Tankages, Supp.structures, Chimney for 8 x 16 MW Kozhikode Diesel Power Project at Nallalam, Kerala

Site
Nallalam, Kerala.

Client
M/s Wartisila NSD India Limited, Chennai

Customer
M/s. Kerala State Electricity Board

Project Duration

Our Scope of Work
Engine & Accessories, Piping, Tanks, Chimnney.


Date of Completion
1999
Name of work
Erection of Engine, Fabrication & Erection of Tanks, Structural and Piping for 2 x 8R32 Power Plant for M/s Praxair

Site
Chennai

Client
M/s Wartisila NSD India Limited, Chennai

Customer
M/s Praxair Pvt. Ltd., Chennai

Project Duration

Our Scope of Work
Engine & Auxiliary Equipment, Tanks, Piping, Structural, Chimney & Duct
demon slayer cosplay costumes

Date of Completion
1999
Name of work
Supply and Erection of DG Power Plant for M/s. Sterlite Industries Phase-III Project.

Site
Tuticorin, Tamil Nadu, india

Client
M/s. Wartsila India Ltd., Chennai

Customer
M/s. Sterlite Industries Ltd

Project Duration
6 Months

Our Scope of Work
 - Supply, Fabrication and Erection of Tanks ( Fresh lube oil, Lube oil service, & Surge tanks), Chimney, Structures & Ducts, Modification of existing tanks
 - Chimney, Supporting Structures, Silencers, Ducts, Platforms sac goyard pas cher

Date of Completion
2003
Name of work
Modification of Fludized Bed Heat Exchangers at Unit 1&2 of NLC TS-II expansion 2x250MW CFBC Boiler at Neyveli TPS.

Site
Neyveli, Cuddalore District, TN, India

Client
M/s. BHEL - PSSR, Chennai

Customer
M/s. Neyveli Lignite Corporation Ltd, Chennai

Project Duration
12 Months

Our Scope of Work
Modification of Fludized Bed Heat Exchangers

Date of Completion
July 2015
Name of work
Mechanical Erection, Testing and Commissioning of Power Cycle Piping of Unit#3&4,phase-II,2X500MW for Simhadri Super Thermal Power project.

Site
Vishakapatnam, AP, India

Client
M/s. BHEL-PSSR, Chennai

Customer
M/s. National Thermal Power Corporation Ltd.,

Project Duration
15 Months

Our Scope of Work
Pressure Parts, Non-Pressure Parts, Air PreHeaters, Duct etc replicas bolsos.

Date of Completion
2011
Name of work
Erection of BTG & its auxiliaries for 2 x 600 MW Mutiara Thermal Power Project

Site
Tuticorin, Tamil Nadu, India

Client
M/s. Coastal Energen Private Ltd, Chennai

Customer
M/s. Coastal Energen Private Ltd, Chennai

Project Duration
33 Months

Our Scope of Work
 - Boiler & its auxiliaries
 - Tubine Generator & its auxiliaries, ESP
 - Electrical works of BTG
 - Instrumentation works of BTG

Date of Completion
2016
Name of work
Mechanical Erection of Boiler for Unit-II, 2x500MW Thermal Power Project

Site
Tuticorin, Tamil Nadu, India

Client
M/s. BHEL - PSSR, Chennai

Customer
M/s. NLC Tamilnadu Power Limited (a JV of NLC Ltd

Project Duration
22 Months

Our Scope of Work
Boiler & its Auxiliaries

Date of Completion
2015
Name of work
Electrical Package of Unit-I & II, 2x500MW NTPL Thermal Power Project

Site
Tuticorin, Tamil Nadu, India

Client
M/s. BHEL - PSSR, Chennai

Customer
M/s. NLC Tamilnadu Power Limited (a JV of NLC Ltd

Project Duration
12 Months

Our Scope of Work
Erection & installation of Electrical items, Laying of cables, Cable Trays, Panels, etc.,
hublot replicas de relojes

Date of Completion
2015
Name of work
Control Instrumentation Package works for Boiler & its Auxiliaries, Turbo Generator & its Auxiliaries, Station C&I for Unit #4 and #5 of 5 x 270 MW Thermal Power Plant, Amravati.

Site
Amravati, Maharashtra, India

Client
M/s. BHEL-PSWR, Nagpur

Customer
M/s.RattanIndia Power Ltd (formerly M/s. India Bulls Power Ltd)

Project Duration
10 months

Our Scope of Work
Testing & Installation of C&I Equipments

Date of Completion
2015
Name of work
Electrical Works and C&I Package for HRSG & its auxiliaries, GTG & its auxiliaries, Station C&I for 2 x 150 MW OPG Kutch Project at OPG Power Gujarat Pvt Ltd. Bhadreshwar, Gujarat

Site
Bhadreshwar, Kutch, Gujarat, India

Client
M/s. BHEL - PSWR, Nagpur.

Customer
M/s. OPG Power Gujarat Pvt Ltd.

Project Duration
13 Months

Our Scope of Work
Electrical: Cable Tray & Accessories, JBs PBS, DBs Misc. Steel Structures fabrication, Panels, Racks Enclosures, UPS, Batteries, PLC , Laying of LT Power & Control Cables, etc C&I: Erection & Commissioning of Instruments/Devices /Cells /Probes etc., all types of valves, limit switches, Pressure Guages/ Temp Guages transmitters

Date of Completion
2015
Name of work
Electrical Package - 2A and 2B, of 2 x 500MW,U-III & IV, Sagardighi Super Thermal Power Project, Sagardighi, West Bengal.

Site
Sagardighi, West Bengal, India

Client
M/s. BHEL-PSER, Kolkata

Customer
M/s.West Bengal Power Development Corporation Ltd.

Project Duration
Package 2A: 13months Package 2B: 11months

Our Scope of Work

Cable tray & accessories; Cabling HT/LT Panels, motors, switch gears, other misc equipments
replica patek philippe

Date of Completion
2017
Name of work
Erection of Engine, Fabrication & Erection of Tanks, Structural and Piping for 1 x 16V 32 and 1 x 12V200R Power Plant for Saint Gobain Glass India Ltd., Sriperumbudur, Tamilnadu.

Site
Sriperumbudur, Tamilnadu.

Client
M/s Wartisila NSD India Limited, Chennai

Customer
M/s. Saint Gobain Glass India Ltd.

Project Duration

Our Scope of Work

Engine, Tanks, Piping, Structural, Chimney & Duct. occhiali da sole ray ban outlet


Date of Completion
1999
Name of work
Mechanical Erection, Testing & Commissioning of BTG & its auxiliariesfor 1 x 150 MW Nagai Power Project

Site
Nagapattinam, Tamil Nadu, India

Client
M/s. KVK Energy and Infrastructure Pvt. Ltd., Hyderabad (KVK Nagai Power Ltd)

Customer
M/s. KVK Energy and Infrastructure Pvt. Ltd., Hyderabad (KVK Nagai Power Ltd)

Project Duration
17 Months

Our Scope of Work
Boiler and Auxiliaries, ESP TG & its Auxiliaries, Piping 

Date of Completion
2019
Name of work
Supply, Installation,Testing,commissioning of 6.6KV ,11KV Substation Equipment in CACP II Substation & PDC VII Substation at IGCAR Kalpakkam

Site
Kalpakkam, TN

Client
M/s.Indira Gandhi Centre for Atomic Research (DAE)

Customer
M/s.Indira Gandhi Centre for Atomic Research (DAE)

Project Duration
10 Months

Our Scope of Work
Power Transformer, 11kV HT Panels , 415V LT Panels, Laying of HT & LT Cables,Termination replicas de bolsos de lujo works, Earthing, DB, MCB, Busducts, Battery & Battery chargers, etc.,

Date of Completion
2019
Name of work
Erection, testing and commissioning of 2 x 500 MW TG sets with auxiliaries and integral piping of Unit 3 and 4 at Tarapur Atomic Power Station

Site
Tarapur, Maharashtra, India.

Client
Tarapur, Maharashtra, India.

Customer
M/s. BHEL-PSWR, Nagpur

Consultant
M/s. Nuclear Power corporation of India Ltd

Project Duration
38 Months

Our Scope of Work
Erection of TG & its auxiliaries with integral piping replica patek philippe

Date of Completion
2006
Name of work
PACKAGE-A: Mechanical Erection of Boiler & its auxliaries of 1 x 660 MW unit # 3 including auxiliary boiler for 2x660 MW units at IBV TPS, Banharpalli, Odisha

Site
Banharpalli, Odisha, India

Client
M/s. BHEL-PSER

Customer
M/s. IB Valley TPS Ltd (Orissa Power Generation corporation Ltd)

Project Duration
36 Months

Our Scope of Work
- Boiler & its Auxiliaries  - ESP   - Power Cycle Piping

Date of Completion
COD achieved in DEC-2019
Name of work
R and M works of ESP Unit-II, III and IV of 5 x 200MW Singrauli Thermal Power Station.

Site
Singrauli, Uttar Pradesh

Client
BHEL - Power Sector Northern Region

Customer
NTPC Ltd

Project Duration
18 Months

Our Scope of Work
R and M works of ESP and auxiliaries

Date of Completion
Completed
Name of work
Mechanical Erection,Testing and Commissioning of Boiler & its auxiliaries, ESP for 1 x 525 MW set at Tuticorin TPS Stage IV, Megha Engineering and Infrastructures Limited (MEIL)

Site
Tuticorin, Tamil Nadu

Client
M/s. BHEL- PSSR

Customer
M/s. Megha Engineering and Infrastructures Limited (MEIL)

Project Duration
Boiler and its Auxiliaries : 26 Months ESP: 24 Months

Our Scope of Work
Boiler and Auxiliaries ESP nfl replica jerseys

Date of Completion
Completed
Name of work
Mechanical Erection,Testing and Commissioning of STG and its auxiliaries for 2 x 660 MW, Stage-II, NTPC Tanda Thermal Power Project

Site
Tanda, Uttar Pradesh

Client
M/s. Alstom Bharat Forge Power Pvt. Ltd

Customer
M/s. NTPC Ltd

Project Duration
26 Months

Our Scope of Work
Steam Turbine Generator & its auxiliaries, Piping works (Unit-I and II) disfraces cosplay anime

Date of Completion
Completed
Name of work
Electrical works for Unit 1 and Auxiliary Boiler, Unit 2 of 2 x 500 MW New Neyveli Thermal Power Project

Site
Neyveli, Tamil Nadu

Client
M/s. BHEL-PSSR, Chennai

Customer
M/s. NLC India Limited

Project Duration
26 Months

Our Scope of Work
Electrical works for Unit 1 and Auxiliary Boiler, Unit 2

Date of Completion
Completed
Name of work
Mechanical works of Coke Dry Quenching (CDQ) System Boiler & its Auxiliaries for Jindal Steel & Power , Angul Odisha

Site
Angul, Odisha

Client
M/s. Jindal Steel

Customer
M/s. Jindal Steel

Project Duration
8 months

Our Scope of Work
CDQ Boiler & its auxiliaries

Date of Completion
Completed

COMBINED CYCLE POWER PROJECT (GAS POWER PLANTS)

Name of work
Mechanical works involving Fabrication, Supply and Erection of PAB piping for 1200 MW Den Combined Cycle Power Project.

Site
Dahej SEZ, Dahej Gujarat, India.

Client
M/s. Siemens Ltd.,

Customer
M/s. Torrent Power Ltd.,

Project Duration
18 Months

Our Scope of Work
Mechanical works (Fabrication, Supply and Erection) of PAB Piping

Date of Completion
2013
Name of work
Component steel Erection Work & Supply of Manpower for steel Rectification for the 1200MW DGEN Power Project.

Site
Dahej SEZ, Dahej Gujarat, India.

Client
M/s. Siemens Ltd.,

Customer
M/s. Torrent Power Ltd.,

Project Duration
05 Months

Our Scope of Work
Mechanical works (Component steel erection work & Manpower supply for steel rectification) of PAB Piping

Date of Completion
2013
Name of work
Electro Mechanical Erection works for 1100 MW Sugen Combined cycle Power Plant

Site
Surat, Gujarat, India

Client
M/s. Siemens Ltd.,

Customer
M/s. Torrent Power Ltd.,

Project Duration

Our Scope of Work
 - Temporary Site Power supply works
 - Erection of Gas Diffuser
 - Erection of GTG & its Auxiliaries with associated piping , HRSG & its Auxiliaries, 
 - Electrical & Control Instrumentation works

Date of Completion
2009
Name of work
Electro Mechanical Erection works for 655 MW Paguthan Combined cycle Power Plant

Site
Paguthan, Baruch, Gujarat, India

Client
M/s. Siemens Ltd.,

Customer
M/s. Gujarat Torrent Energy Corporation Ltd

Project Duration
23 Months

Our Scope of Work
Gas Turbine, Steam Turbine, Condenser, Generator, Piping, Auxiliaries , Electrical HT & LT Panels, Cable Laying, Termination & Instrumentation. offical 

Date of Completion
1998
Name of work
Electro-Mechanical Erection works of GTG & its auxiliaries of 382.5 MW Sugen Combined Cycle Power Plant

Site
Sugen, Surat, Gujarat, India.

Client
M/s. Siemens Ltd.,

Customer
M/s. Torrent Power Ltd.,

Project Duration
24 Months

Our Scope of Work
- STG sets & its auxiliaries - GTG & its auxiliaries with integral piping - Electrical and C & I works

Date of Completion
2013
Name of work
Electro Mechanical Erection works for 330 MW Pillaipermanallur CCPP near Myladuthurai

Site
near Myladuthurai, Tharangambadi Taluk, Nagapattinam District, TN, India

Client
M/s MHI, Japan

Customer
M/s. PPN Power Generating Company Private Limited

Project Duration
12 Months

Our Scope of Work
 - GTG & its Auxiliaries, STG & its Auxiliaries, Insulation, Painting, etc.,
 - Electrical & Instrumentation.

Date of Completion
2001
Name of work
Erection, Testing and Commissioning of Balance Controls & Instrumentation works for MRPL Phase- III 122 MW Co-generation Captive Power Plant.

Site
Mangalore, Karnataka, India

Client
M/s. BHEL - PSSR, Chennai

Customer
M/s. MRPL - Mangalore Refinery

Project Duration
12 Months

Our Scope of Work
Associated fabrication & erection works, Testing and Installation of Panels, cabling, impulse pipe, tubing, instruments etc.,

Date of Completion
2015
Name of work
Erection of Fuel Oil Piping for 106.617 MW Combined Cycle Power Plant at Dhuvaran, Gujarat

Site
Dhuvaran, Gujarat

Client
M/s. BSES, NOIDA

Customer
M/s. BSES, NOIDACorporation,Paguthan, Gujarat

Project Duration
5 Months

Our Scope of Work
CS Piping , SS Piping & HSD Tanks.

Date of Completion
2003
Name of work
Electrical works for 95MW Combined Cycle Power Plant at Valuthur, Tamilnadu

Site
Valuthur, Tamil Nadu, India

Client
M/s. GEA Energy Systems, Chennai.

Customer
M/s. Tamil Nadu Electricity Board (TNEB)

Project Duration

Our Scope of Work
Transformers, electrical equipments, Panel,  Cable Trays, Cabling, Termination, HT & LT Bus Ducts and Earthing 

Date of Completion
2003
Name of work
Electrical Package for 1 x 30MW GTG + 1x125TPH HRSG Based co-gen, IOCL(IRUP), Gujarat Refinery, IOCL Vadodara Project(GT#6) at IOCL Gujarat refinery, Vadodara

Site
Vadodara, Gujarat, India

Client
M/s. BHEL-PSWR, Nagpur

Customer
M/s. IOCL-Gujarat Refinery, India

Project Duration
8 Months

Our Scope of Work
Cabling, Transformer , DAVR, Busducts, Switchgear, Lighting Package & Associated Equipments

Date of Completion
2015
Name of work
Civil, Structural, Super structure & architectural works and Electro-Mechanical erection works for 1 x 25MW Cogen Power plant of BPCL Kochi Refinery

Site
BPCL Kochi Refinery, Ambalamugal, Kerala, India

Client
M/s. BHEL-PSSR, Chennai

Customer
M/s. BPCL Kochi Refinery

Project Duration
27 Months

Our Scope of Work
 - Civil, Structural, Super structure & architectural works
 - Erection of GTG & its Auxiliaries with associated piping , HRSG & its Auxiliaries, 
 - Electrical & Control Instrumentation works

Date of Completion
2011

SUB STATION PROJECT

Name of work
Erection, Testing & Commissioning of 123 KV /33 KV Gas Insulated Sub-Stations at Seven Wells, High Court and Jogirthottam in Chennai

Site
Chennai, Tamilnadu, India

Client
M/s Shaanxi Machinery

Customer
M/s Tamil Nadu Electricity Board(TNEB) , Chennai

Project Duration

Our Scope of Work
123 KV Bays Feeders Transformers , 123 KV Bus Disconnectors with Earthing Switch 123 KV Bus Bar, VT's & Earthing Switch Replica Rolex Watches Replica swiss Watches

Date of Completion
1999

NUCLEAR POWER PROJECT

Name of work
Erection of Carbon Steel Liner and support steel works of reactor for 2 X 1000 MW Atomic Power Plant

Site
Kudankulam, Tuticorin District, Tamil Nadu

Client
M/s. HCC Ltd., Mumbai

Customer
M/s. NPCIL

Project Duration
24 Months

Our Scope of Work
Steel Liner Fabrication & Erection

Date of Completion
2005
Name of work
Erection, testing and commissioning of TG sets with auxiliaries for 2 X 236 MW Kakrapar Nuclear Power Station Project

Site
Kakrapar, Gujarat

Client
M/s. BHEL-PSWR, Nagpur

Customer
M/s. Nuclear Power corporation of India Ltd

Project Duration
40 Months

Our Scope of Work

Mechanical Erection of TG sets, Static Excitation System and Associated Auxiliaries & Piping


Date of Completion
1994

DIESEL POWER PROJECT

Name of work
Erection of Chimney, Tanks and Structurals for the 106 MW DG based Samalpatti Power Project.

Site
Samalpatti,Dharmapuri District, Tamil nadu

Client
M/s.Wartsila India Ltd.,Chennai

Customer
M/s Samalpatti Power Corporation Ltd

Project Duration
6 Months

Our Scope of Work
HFO Tanks, LFO Tanks, Service Tanks & Chimney

Date of Completion
2001
Name of work
Electro-Mechanical Erection works for 200MW Diesel Engine Power Plant at Basin Bridge, Chennai

Site
Chennai, Tamil Nadu

Client
M/s. Hyundai Heavy Industries Ltd., Korea.

Customer
M/s. GMR Vasavi Power Corporation, Chennai.

Project Duration

Our Scope of Work
 - Equipments, CS Piping (IBR & Non IBR), GI Piping, Painting & Insulation
 - Transformer & Electrical Equipment, Bus Ducts, Cabling, Cable Tray, Conduits, Earthing & Lighting.

Date of Completion
1999
Name of work
Erection of fabricated Tanks and Chimney for 3 x 6 MW DG Sets of Tamilnadu Petroproducts Ltd., Manali

Site
Manali, Chennai, Tamilnadu, india

Client
M/s. Wartsila India Ltd., Chennai

Customer
M/s. Tamilnadu Petroproducts Ltd.

Project Duration

Our Scope of Work
Storage Tanks, Chimney, structurals, Ducts & Platforms.

Date of Completion
2002

SOLAR

Name of work
Agency for Nonconventional Energy and Rural Technology (ANERT) 80kWp Rooftop solar project at Pothanikkad Grama Panchayat in Ernakulam District, Kerala

Site
Pothanikkad Grama Panchayat in Ernakulam District, Kerala.

Client
ADTECH systems

Customer
Agency for Nonconventional Energy and Rural Technology (ANERT)

Project Duration

Our Scope of Work

Date of Completion
2018
Name of work
Design, Engineering, Supply & Construction of Roof Top Solar Panels at Ramakrishna Mission Vivekananda Centenary Girls Higher Secondary School, Mint and Charitable Dispensary, Mylapore in Chennai (under NLC CSR during 2018-19)

Site
Chennai, Tamilnadu

Client
M/s. NLC India Ltd

Customer
M/s. NLC India Ltd

Project Duration
3 months

Our Scope of Work
Engineering Procurement of 52kWp Rooftop solar -> Civil works , Solar Polycrystalline SPV modules, Grid Inverters, Structures, Electrical BoS, Firefighting, Netmetering, etc.,

Date of Completion
2019
Name of work
Design, Enginering, Supply, Installation of 30kWp Ongrid Connected ground mounted Solar Plant

Site
Cuddalore, Tamilnadu

Client
M/s. NLC India Ltd

Customer
M/s. NLC India Ltd

Project Duration
4 months

Our Scope of Work
Design, Enginering, Supply, Installation of 30kWp Ongrid Connected ground mounted Solar Plant Replica Rolex Watches Replica swiss Watches

Date of Completion
2020

TRANSMISSION & DISTRIBUTION

Name of work
Rural electrification works involving 11KV & LT Lines at Gosani block in Gajapati district Odisha under RGGVY

Site
GAJAPATI District, GOSANI block in Odisha

Client
BENZFAB Technologies Pvt Ltd

Customer
NTPC / NSIC

Project Duration
7 months

Our Scope of Work
Site Survey, Planning, Design, Engineering, Supply of Equipments &   Installation     works for Rural Electrification works  in Gosani Block 11KV Tranmsission lines - 26 KM , LT Lines - 463.5KM costume cosplay pas cher Installation of Distribution Transformers Providing service connection to BPL consumers, etc.,

Date of Completion
2018
Name of work
Supply, Erection, Testing and commissioning of (i) 132/33kV SS at Kotagiri, (ii) 132KV DC/SC line, (iii) 132kV Bay extension at 132/33kV SS Jakora in Nizamabad District

Site
Kotagiri, Nizamabad district

Client
M/s. ICoat Project Pvt. Ltd

Customer
M/s. TSTRANSCO, Ltd

Project Duration
12 months

Our Scope of Work
(i) 132/33kV SS at Kotagiri, Nizamabad District
(ii) 132KV DC/SC line (16km) from 132/33kV Jakora Substation to Proposed Kotagiri SS,
(iii) 132kV Bay extension at 132/33kV SS Jakora in Nizamabad District
borse firmate imitazioni perfette

Date of Completion
2018