EPC & Turnkey

EPC & TURNKEY PROJECTS

Name of work
Lumsum Turnkey (LSTK) of Balance of Plant (BoP) package for 1 x 350 MW Thermal Power Plant - KVK Nilachal Power Pvt. Ltd.,

Site
Cuttack, Odisha, India

Client
M/s. KVK Nilachal Power Pvt. Ltd.

Customer
M/s. KVK Energy

Project Duration
18 Months

Our Scope of Work
Design, Engineering, Supply and Erection of Balance of Plant (BoP) Packages
 - Coal Handling Package
 - Ash Handling Package
 - Water System package (CW & ACW, WTP)
 - Fire Detection & Protection System
 - Fuel Oil Handling System
 - Heat Ventilation & Air Conditioning System
 - Piping
 - Cooling Tower
 - Electrical Balance of Plants (E-BoP) & Switchyard
 - Associated Control & Instrumentation works

Date of Completion
Ongoing
Name of work
LSTK of Balance of Plant (BoP) package for 2 X 350 MW Coastal Thermal Power Project.

Site
Krishnapatinam,Andhra Pradesh, India

Client
M/s. CCCL-EDAC Energy Ltd., Chennai.

Customer
M/s. Meenakshi Energy Private Ltd., Noida ( GDF Suez)

Project Duration
30 Months

Our Scope of Work
Design, Engineering, Supply and Erection of Balance of Plant (BoP) Packages
 - Coal Handling Package
 - Ash Handling Package
 - Water System package (CW & ACW, WTP)
 - Fire Detection & Protection System
 - Heat Ventilation & Air Conditioning System
 - Piping
 - Induced Draft Cooling Tower
 - Fuel Oil Handling System
 - Electrical Balance of Plants (E-BoP) & Switchyard
 - Associated Control & Instrumentation works

Date of Completion
Ongoing